On this page you will find the chronology of the expansion of our production and storage facilities, which began in May 2016 with the purchase of a new site at Jahnstraße 6 in Brunsbüttel, Northern Germany.
Expansion of the storage area (2019)
After the expansion of the production and administration area had already been successfully completed for two years, construction of a new warehouse commenced at the beginning of 2019.
Below you can see the construction site in a time lapse of one year: The picture above left shows the construction area before the start of the construction project (June 2018), the picture below right the status of construction work in April 2019.
|
![]() |
![]() |
|
Expansion of production (2016 - 2017)
In September 2016, work started on the expansion of the production facility and the construction of the new administration wing. A new fence was erected along the new site boundaries. Then the demolition of the old building could begin:
|
|
|
|
Start of construction (Section 1):
At the end of October, the earthworks could begin. First, the excavation for the construction road was started to secure the access road for the extension building. Foundation work then began between the two existing wings of the production plant:
The excavation was finished, and the area was filled with new load-bearing soil:
|
|
|
|
The excavation is finished and the area is filled with new load-bearing soil:
|
|
|
|
Start of construction (Section 2):
After the foundation was completed, the casting of the base plate for the 500 m2 large extension followed, which will include the new dispatch centre and the goods receiving area in addition to another SMD line.
|
|
|
|
Time is passing by and so is our new building. After the concrete has dried we started with the hall construction. Meanwhile the side parts are standing, and the roof construction is finished. The roof will be covered before Christmas and we can celebrate the topping-out ceremony!
The large skylight dome in the middle of the hall, which will provide a good atmosphere and daylight, can be seen beautifully. This is part of the sustainable energy concept of the new building, which will provide low energy consumption in addition to low heat requirements, as the ventilation will be demand-driven.
|
|
|
|
Now the roof has been put on!
|
|
|
|
The office building is now also being constructed and the production extension has received the skylight dome and the side walls:
|
|
|
|
The office building has also been completed and is now getting its roof. The topping-out ceremony can come!
|
|
|
|
Start of construction (Section 3):
The hall is ready, and we celebrated the topping-out ceremony on 09 February 2017. Now section 3 of the interior construction begins. It's nice to see on the new pictures that the construction work on the office building is almost finished and that the interior work can be started there as well.
|
|
|
|
Final construction phase and move into the administration building:
Finally, the time has come! Since the end of May 2017, the administration is now located at Jahnstraße 6 and the purchasing department has also moved from Annastraße 14 to the new office building. In the production hall, the third line with an ERSA HotFlow 4/20 will be put into operation within the next few days.
The third hall will be completed at the end of June and will house the new logistics and spare parts centre.
|
|
![]() |
|